#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
101MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)Jiribamx7009/09/2025
102MSPCLC30Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV LILO line & related civil works at Paoyi, Ukhrul District.POWER (MSPCL)UkhrulX8519/03/2025
103MSPCLC48Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Kachai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrulx70%01/03/2025
104MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)Jiribamx70%
105MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)Jiribamx6001/03/2025
106MSPCLC5Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi KhullenPOWER (MSPCL)UkhrulX10015/03/2018
107MSPCLC5Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi KhullenPOWER (MSPCL)UkhrulX10015/03/2018
108MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018
109MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018
110MSPCLC21Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai.POWER (MSPCL)Imphal-WestX100 percent completed22/02/2018
111MSPCLC21Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai.POWER (MSPCL)Imphal-WestX100 percent completed22/02/2018
112MSPCLC50Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Khongjaron, Tamenglong District on turn key baPOWER (MSPCL)Tamenglongx81%23/03/2026
113MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018
114MSPCLC6Installation of 2x5 MVA, 33/11 kV Sub-Station at MayangkhangPOWER (MSPCL)SenapatiX100 %
115MSPCLC6Installation of 2x5 MVA, 33/11 kV Sub-Station at MayangkhangPOWER (MSPCL)SenapatiX100 %21/01/2020
116MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% 21/01/2020
117MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed21/01/2020
118MSPCLC29Installation of 2x2.25 MVA, 33 kV LILO line & related civil works at Thuyeng, Senapati District.POWER (MSPCL)Senapatix8511/12/2025
119MSPCLC21Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai.POWER (MSPCL)Imphal-WestX100 percent completed22/02/2018
120MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed21/01/2020