| 201 | MSPCLC21 | Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai. | POWER (MSPCL) | Imphal-West | X | 100 percent completed | 22/02/2018 |
| 202 | MSPCLC8 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Ukhrul Khunjao with associated 33 kV line and related civil works | POWER (MSPCL) | Ukhrul | X | 100 | 24/11/2017 |
| 203 | MSPCLB8 | Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformer | POWER (MSPCL) | Tamenglong | X | 80% | 21/03/2018 |
| 204 | MSPCLC46 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Liyaikhunou, Senapati District | POWER (MSPCL) | Senapati | x | 85 | 08/09/2025 |
| 205 | MSPCLC50 | Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Khongjaron, Tamenglong District on turn key ba | POWER (MSPCL) | Tamenglong | X | 60% | 01/03/2025 |
| 206 | MWSP_PHED_NDB | Manipur Water Supply Project (NDB) | PHED | Others | Work package: RWS P-IX (W) | On going | 24/06/2022 |
| 207 | MWSP_PHED_NDB | Manipur Water Supply Project (NDB) | PHED | Others | Work package: RWS P-IX (W) | On going | |
| 208 | MWSP_PHED_NDB | Manipur Water Supply Project (NDB) | PHED | Others | Work package: RWS P-IX (W) | On going | 24/06/2022 |
| 209 | MWSP_PHED_NDB | Manipur Water Supply Project (NDB) | PHED | Others | Water supply project at Wangjing Town WSS | Ongoing | 06/05/2022 |
| 210 | IPDI/TRAININGCENTERCUMCONFEENCEHALL | Construction of Training Center Cum Conference Hall, P.H.E.D | PHED | Imphal-West | water supply | in progress | 26/03/2026 |
| 211 | WRD-FCW-276 | Re-sectioning of Laija Stream from Imphal Low Level Canal to Sanlou Loukut mapa | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 22/06/2022 |
| 212 | WRD-FCW-278 | Re-sectioning of Koirenkhong Stream from RD 0.00 m to RD 1000.00 m | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 21/06/2022 |
| 213 | WRD-FCW-279 | Temporary closing breach portion of Thongjaorok River at Patlou Lambi, Kwakshiphai | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 21/06/2022 |
| 214 | WRD-FCW-338 | Restoration work on river bund on LBB of Thangtek River at Hidaksungbam mapa at Thangtek. | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 22/11/2022 |
| 215 | WRD-FCW-302 | Improvement of Poangnao Turel at DS of Tiddim Rd. at Leimaram Lamkhai. | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 18/11/2022 |
| 216 | WRD-FCW-331 | Improvement of Tera Urak Stream from Tiddim road culvert to Loktak. | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 18/11/2022 |
| 217 | WRD-FCW-303 | Improvement of Keinou River | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 18/11/2022 |
| 218 | WRD-FCW-332 | Improvement of Lamnganbi Stream from Imphal Low Level Canal to Tiddim Road. | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 18/11/2022 |
| 219 | WRD-FCW-278 | Re-sectioning of Koirenkhong Stream from RD 0.00 m to RD 1000.00 m | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 21/06/2022 |
| 220 | WRD-FCW-279 | Temporary closing breach portion of Thongjaorok River at Patlou Lambi, Kwakshiphai | Water Resources Department (WRD) | Bishnupur | WAB 2022-2023 | Completed | 21/06/2022 |