261IWD/Changangei Makha-Ningthoujam Pukhri/127Impvt. of Internal Road from Changangei Makha Leikai to Ningthoujam Pukhri Taba LambiPWDImphal-West----Completed08/10/2024
262IED/Chandam Leirak-Chandam Mayai/911Impvt. of road from Chandam Leirak to Chandam Mayai LeikaiPWDImphal-East----Completed 09/02/2026
263SE-I/DRP/IE/22-2/R1.48 NH-2 to Lilando LampakImpvt. of road from NH-2 to Lilando Lampak MachinPWDImphal-East----Completed20/08/2024
264IED/Western side-Thambalkhong thong-angom/880Impvt. of road along western side of Iril river fromThambalkong thong to angom thongPWDImphal-East----Completed
265SE-I/DAR/23-24/IE-R1.46 Langdum to Keirao RdImprovement of road at Langdum to Keirao Road.PWDImphal-East----100%04/02/2025
266IWD/Moiranghanuba-Heinoupok/163Impvt. of Moiranghanuba Sadokpam to Heinoupok road and its neighbouring lanesPWDImphal-West----Completed30/01/2025
267IED/Heingang CD Block/781Constn. of Heingang CD Block (SH: Constn. of Bank Type-IV Qtr)-PWDImphal-East----completed30/10/2024
268IED/Keibi Kumuda Taretkhul/878Improvement of Keibi Kumuda Taretkhul IVR Ring roadPWDImphal-East----On going16/08/2024
269IED/NH39-Kakwa Bazar-Ningomthong bridge/233Impvt. of road from NH-39 (NH-2) Kakwa Bazar to Ningomthong Bridge via Lilando Lampak, Nongmeikapam Leirak, Sairom Leirak, Beni Leirak, Thongbam ....PWDImphal-East----Completed
270SE-I/DAR/23-24/IE-R1.60 Khongman MangjilImpt of road from Khongman Mangjil to Sangaipat including Southern side of Nahabam roadPWDImphal-East----Completed 30/08/2024
271SE-I/DAR/22-23/IE.R1.78 Classic Grande RoadImpvt. of Classic Grande road from Dingku road up to NH-2 i/c 2 Nos of 1 m span culvertsPWDImphal-East----Completed20/02/2025
272No.SE-1/DAR/23-24/IE-R1.3 Pangei to TezpurImprovement of road from Pangei to Tezpur including Waiton internal roadPWDImphal-East----work in progress03/09/2024
273SE-I/BDG/DRP/2022-23/C1/382-2 Kongba riverConstruction of Bridge over Kongba river at Kongba Uchekon (SH:- Construction of Approach Road and Retaining Wall)PWDImphal-East----Work Completed 21/01/2025
274SE-I/DAR/23-24/IE-Rc.89 Drain Nagaram Block-DConstruction of drainage around 1.5 km and two culvert at Nagaram block-D, Little clinic roadPWDImphal-East----ongoing work12/08/2024
275IED/Canchipur-Irilbung/234Impvt. of road from Canchipur MU gate (NH-39) to Irilbung via Jubraj Palli, Koirou, Bashikhong, Panthoibi Bazar and Konok Khongnangkhong (12.92 Km ..PWDImphal-East----Completed13/02/2025
276IED/In & around Nagaram/752Impvt. of road in and around Nagaram i/c construction of pucca line drain near Little Clinic Hospital approach road.PWDImphal-East----Completed23/08/2024
277IWD/Wapokpi-Changangei/100Impvt. of road from Wapokpi at Langjing Bazar to Changangei connecting NH-150PWDImphal-West----completed08/10/2024
278D-IV/LILONG HAOREIBI/CFMInfrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Lilong Haoreibi College,Thoubal, ManipurEducation (S)Thoubal..20/11/2025
279D-IV/Y.K/CFMInfrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Y. K. College,Thoubal, Manipur.Education (S)Thoubal..20/11/2025
280MSPCLC46Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Liyaikhunou, Senapati DistrictPOWER (MSPCL)Senapati.70%01/03/2023