| 341 | CSC/Takhok Awang | Construction of CSC | PHED | Imphal-East | NA | 100 percent | 17/02/2021 |
| 342 | IED/Keibi Kumuda/338 | Improvement of Keibi Kumuda Ring Road (SH:WBM/PC) | PWD | Imphal-East | 2 | 100 percent | 19/09/2022 |
| 343 | CSC/Bashikhong | CSC Bashkhong Panthoibi Lampak | PHED | Imphal-East | NA | 100 percent | 17/02/2021 |
| 344 | CSC/Koirou | Construction of CSC | PHED | Imphal-East | NA | 100 percent | |
| 345 | CSC/Wangkhei Loumanbi | CSC at Wangkhei Loumanbi | PHED | Imphal-East | NA | 100 percent | 17/02/2021 |
| 346 | CSC/Uchekon | CSC at Uchekon Atom Leirak | PHED | Imphal-East | NA | 100 percent | 17/02/2021 |
| 347 | CSC/Bashikhong | CSC Bashkhong Panthoibi Lampak | PHED | Imphal-East | NA | 100 percent | 17/02/2021 |
| 348 | MSPCLC20 | Construction of 2x5 MVA, 33/11 kV SS at Sugnu along with association 33 kV line & related civil works on turn key basis under NLCPR | POWER (MSPCL) | Thoubal | Nil | 100 percent Complete | 22/02/2018 |
| 349 | MSPCLC9 | Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at Gelnel | POWER (MSPCL) | Kangpokpi | X | 100 percent Completed | 23/02/2018 |
| 350 | MSPCLC21 | Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai. | POWER (MSPCL) | Imphal-West | X | 100 percent completed | 22/02/2018 |
| 351 | MSPCLC21 | Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai. | POWER (MSPCL) | Imphal-West | X | 100 percent completed | 22/02/2018 |
| 352 | MSPCLC21 | Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai. | POWER (MSPCL) | Imphal-West | X | 100 percent completed | 22/02/2018 |
| 353 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 354 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 355 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 356 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 357 | MSPCLC9 | Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at Gelnel | POWER (MSPCL) | Kangpokpi | X | 100 percent Completed | 23/02/2018 |
| 358 | MSPCLC21 | Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai. | POWER (MSPCL) | Imphal-West | X | 100 percent completed | 22/02/2018 |
| 359 | MSPCLC26 | Installation of 33/11 kV Sub-station at Gamphazol with associated 33 kV line | POWER (MSPCL) | Senapati | X | 100 percent completed | 06/03/2019 |
| 360 | MSPCLC26 | Installation of 33/11 kV Sub-station at Gamphazol with associated 33 kV line | POWER (MSPCL) | Senapati | X | 100 percent completed | 26/02/2019 |