Progress
 
 
Project Details
DAR-2024-000963
D-IV/PRESIDENCY COLLEGE/CFM
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at PRESIDENCY COLLEGE,Kangpokpi, Manipur
10/10/2023
Education (S)
Kangpokpi
250.00
0.00
CSS / CPS
2nd slab
2rd
24.999396674092335,93.90074054974366
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Presidency College,Kangpokpi, Manipur. Part A & B
Progress Update : 22/11/2025
2nd slab
2rd
so9.eew
24.999396674092335,93.90074054974366
24.9989725,93.9003001
0.06476481682226
0
construction of classroom for block B

Progress Update : 22/11/2025
2nd slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.9988977,93.9002207
0.076305236179787
0
block A & B

Progress Update : 22/11/2025
2nd slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.9989664,93.9001
0.080346456411134
0
construction of classroom for block A

Progress Update : 22/11/2025
2nd slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.9989696,93.9000961
0.080451987914093
0
construction of classroom Block A

Progress Update : 22/11/2025
The work has been complete upto casting slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.999558,93.9007559
0.018004333210819
0
construction of classroom for block A

Progress Update : 22/11/2025
The work has been complete upto casting slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.9993828,93.9004745
0.026854995958719
0
construction of classroom in front view , Block B

Progress Update : 22/11/2025
upto 2nd roof slab
2nd
so9.eew
24.999396674092335,93.90074054974366
24.9947868,93.8991053
0.53840887577137
0
construction of classroom side view,block B

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9994391,93.8992704
0.14822566467138
0
construction of classroom block -b

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9991206,93.9002114
0.06152815033843
0
construction of classroom Block -a

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9989077,93.900309
0.069621967380802
0
construction of classroom Block b

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9992033,93.9001147
0.066632988120762
0
construction of classroom block b

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9991278,93.9007877
0.030271146016397
0
construction of classroom block A

Progress Update : 21/12/2024
The work has been complete upto slab
1st
so9.eew
24.999396674092335,93.90074054974366
24.9992521,93.9005221
0.027258181914858
0
construction of classroom block a

Progress Update : 21/12/2024
completed upto casting of 1st floor
1st
so9.eew
24.999396674092335,93.90074054974366
24.9990244,93.9002024
0.068222905895936
0
construction of classroom block -B