Progress
 
 
Project Details
DAR-2026-000134
SPT/Repair of IVR Road of 2.5km at Bailampou
Repair of IVR Road of 2.5km at Bailampou
16/04/2026
PWD
Senapati
100.00
0.00
sASCI
Completed
1
25.400440,94.113046
Repair of IVR Road of 2.5km at Bailampou under Lairouching sub div,spt, barak fest 2025
Progress Update : 28/04/2026
Completed
1
eesptd
25.400440,94.113046
25.4014526,94.1197495
0.68265296286838
0
Hill cutting, GSB,WBM,PC

Progress Update : 28/04/2026
Completed
1
eesptd
25.400440,94.113046
25.401409,94.1186261
0.57073125780477
0
Hill Cutting, GSB,WBM,PC

Progress Update : 28/04/2026
Completed
1
eesptd
25.400440,94.113046
25.4016331,94.1188631
0.59914418884494
0
Hill cutting, GSB, WBM, PC

Progress Update : 28/04/2026
Completed
1
eesptd
25.400440,94.113046
25.4021812,94.1182639
0.55870413489929
0
Hill Cutting, GSB, WBM,PC

Progress Update : 28/04/2026
Completed
1
eesptd
25.400440,94.113046
25.4013588,94.1150421
0.22501777312959
0
Hill cutting, GSB, WBM. PC