Progress
 
 
Project Details
02_Jivan_Hospital
proposal for setting up of Emergency and trauma Care Unit at Jivan Hospital, Kakching, Thoubal District
2013-12-20
Planning Department
Kakching
467.13
280.00
NEC
Ongoing (53.61%)
2nd Installment
24.49619929999999,94.00347190000002
Installation of Machines & Equipment for Emergency & Trauma Care
Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:56:47
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:57:04
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:55:04
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:57:22
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:57:40
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:58:05
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:59:17
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:58:27
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 08:59:39
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:00:09
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 09:00:47
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:01:07
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:03:30
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4958676,94.0033964
0.037664537489647
Approved
2017-08-18 09:01:26
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:01:47
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:03:09
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4961545,94.0034961
0.0055508101458645
Approved
2017-08-18 09:03:46
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 09:04:02
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.5047938,93.9776277
2.7840074845568
Approved
2017-08-18 08:54:32
approvernec
0
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Progress Update : 2017-07-17
Ongoing (53.61%)
2nd Installment
jivanhospitalkak
24.49619929999999,94.00347190000002
24.4974854,94.0068207
0.36777412280557
Approved
2017-08-18 08:53:17
approvernec
280
Equipment and Machinery funded by NEC for Emergency and Trauma Care Unit

Foundation & Inauguration
-
-
-

-
-
-