Progress
 
 
Project Details
DAR-2018-001280
BRD/Bridge-Sun Light Club/24
Constn. of RCC Bridge Kongba River at Sun Light Club Mapa
2018-03-28
PWD
Imphal-East
300.00
197
State Plan
Completed
Final
24.781835173168698,93.95796793450165
Progress Update : 2026-01-30
Completed
Final
so1brd3
24.781835173168698,93.95796793450165
24.7820585,93.9578267
0.028633695518966
Approved
2026-01-30 10:11:52
se1pwd
197
Both Main bridge approach road, banking, shingling and gravity retaining wall are completed

Progress Update : 2025-02-28
completed
final
so1brd3
24.781835173168698,93.95796793450165
24.7818513,93.9573189
0.065544634002178
Approved
2026-01-30 10:09:51
se1pwd
197
Main Bridge completed.

Progress Update : 2021-06-26
Ongoing
2
so1brd2
24.781835173168698,93.95796793450165
24.7821247,93.9578984
0.03294875948147
Approved
2022-09-09 05:24:53
se1pwd
100
Both the abutments and a pier is in progress

Progress Update : 2021-02-14
Ongoing
Initial
so1brd2
24.781835173168698,93.95796793450165
24.7836875,93.9577154
0.20753119205159
Approved
2021-02-16 07:29:35
se1pwd
0
Piles of one side abutment

Progress Update : 2019-09-28
Not yet started
Initial
so1brd
24.781835173168698,93.95796793450165
24.7845378,93.9599035
0.35844281339551
Approved
2021-02-12 08:22:49
se1pwd
0
This work is under state plan

Progress Update : 2019-09-28
Not yet started
Initial
so1brd
24.781835173168698,93.95796793450165
24.7845378,93.9599035
0.35844281339551
Approved
2019-10-03 07:44:21
ace3pwd
0
This work is under state plan

Foundation & Inauguration
-
-
-

-
-
-