Progress
 
 
Project Details
DAR-2018-001351
Ukl/Link road/Ukhrul/36
Improvement of link road Ukhrul Town.
2018-02-26
PWD
Ukhrul
300.00
284.31
State Plan
Completed
1
25.10337633510905,94.36481267373654
E/W, Shingling, WBM, RC, RW - 4.5m, Pucca Drain & approach road
Progress Update : 2022-10-13
Completed
1
eeukld
25.10337633510905,94.36481267373654
25.1029636,94.3618121
0.30558498546407
Approved
2022-10-18 07:21:11
pwdse2ce
284.31
GSB WBM overlaid with PC & SC

Progress Update : 2022-10-13
Completed
1
eeukld
25.10337633510905,94.36481267373654
25.0881118,94.3637392
1.7006956845456
Approved
2022-10-18 07:26:03
pwdse2ce
284.31
PC & SC

Progress Update : 2022-10-13
Completed
1
eeukld
25.10337633510905,94.36481267373654
25.0881118,94.3637392
1.7006956845456
Approved
2022-10-18 07:15:47
pwdse2ce
284.31
PC

Progress Update : 2022-10-13
Completed
1
eeukld
25.10337633510905,94.36481267373654
25.0881118,94.3637392
1.7006956845456
Approved
2022-10-18 07:17:21
pwdse2ce
284.31
WBM overlaid with PC & SC

Progress Update : 2021-02-25
95%
1
eeukld
25.10337633510905,94.36481267373654
25.084845928371,94.357990242115
2.1718986869342
Approved
2021-03-11 07:17:25
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2021-02-25
95%
1
eeukld
25.10337633510905,94.36481267373654
25.084845928371,94.357990242115
2.1718986869342
Approved
2021-03-11 07:18:45
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2021-02-25
100% completed
1
eeukld
25.10337633510905,94.36481267373654
25.084845928371,94.357990242115
2.1718986869342
Approved
2022-10-18 07:28:04
pwdse2ce
284.31
Completed up to PC & SC

Progress Update : 2021-02-25
95%
1
eeukld
25.10337633510905,94.36481267373654
25.084767392468,94.357693657205
2.1897783765338
Approved
2021-03-11 07:20:00
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2021-02-25
95%
1
eeukld
25.10337633510905,94.36481267373654
25.084767392468,94.357693657205
2.1897783765338
Approved
2021-03-11 07:20:38
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2021-02-25
100%
1
eeukld
25.10337633510905,94.36481267373654
25.0849897,94.3566735
2.2025613795522
Approved
284.31
PC & SC surface completed

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.092263933,94.358922973
1.3705351396513
Approved
2021-03-11 07:22:43
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.0970738,94.3608486
0.8064743770737
Approved
2021-03-11 07:21:59
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.092088633,94.35847877
1.4078228456878
Approved
2021-03-11 07:23:24
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:24:10
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:24:49
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:25:45
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:26:40
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:27:38
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.091238112079,94.36288190835
1.3635743129592
Approved
2021-03-11 07:28:22
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.208846373184,94.460891435862
15.199662186319
Approved
2021-03-11 07:29:16
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.208846373184,94.460891435862
15.199662186319
Approved
2021-03-11 07:30:18
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-12-12
95%
1
eeukld
25.10337633510905,94.36481267373654
25.208846373184,94.460891435862
15.199662186319
Approved
2021-03-11 07:31:03
pwdse2ce
0
Physical progress of the work Financial break-up Physical progress 1) GSB 3.17% 100% 2) WBM 33.85% 100% 3) PC 2.83% 95% 4) Pucca Drain 2.51% 100% 5) Formation Widening 8.25% 100% 6) Retaining wall 13.37% 100%

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:03:22
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:05:51
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:08:16
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:06:34
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:07:33
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:08:51
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:09:31
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102933471,94.364251682
0.074935170304111
Approved
2020-03-16 07:10:21
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.0909045,94.3649594
1.3868167699765
Approved
2020-03-16 07:11:06
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-03-13
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.0909045,94.3649594
1.3868167699765
Approved
2020-03-16 07:11:48
pwdse2ce
0
R/wall, drain, WBM, PC

Progress Update : 2020-01-31
Ongoing WBM
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:13:08
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing WBM
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:14:05
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing WBM
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:15:05
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:15:36
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:16:15
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:16:48
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:17:27
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:18:18
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.102498024,94.369185858
0.45102437287335
Approved
2020-03-16 07:19:04
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.090403810748,94.357766391826
1.6074654255518
Approved
2020-03-16 07:19:35
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.090403810748,94.357766391826
1.6074654255518
Approved
2020-03-16 07:20:28
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.090403810748,94.357766391826
1.6074654255518
Approved
2020-03-16 07:21:32
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.090403810748,94.357766391826
1.6074654255518
Approved
2020-03-16 07:25:56
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.090403810748,94.357766391826
1.6074654255518
Approved
2020-03-16 07:23:40
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:26:49
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:29:15
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:27:34
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:30:41
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:31:42
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
25.084851039351,94.358170826148
2.1656752084539
Approved
2020-03-16 07:32:27
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-31
Ongoing
2
eeukld
25.10337633510905,94.36481267373654
24.81415234216,93.932372481334
54.17080887792
Approved
2020-03-16 07:34:15
pwdse2ce
0
Shingling, WBM, PC, Pucca Drain, Rwall

Progress Update : 2020-01-26
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0873245,94.3583649
1.8992168816545
Approved
2020-03-16 07:32:54
pwdse2ce
0
WBM, PC

Progress Update : 2020-01-26
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0968289,94.3691997
0.85153836360631
Approved
2020-03-16 07:33:35
pwdse2ce
0
WBM, PC

Progress Update : 2020-01-26
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0873245,94.3583649
1.8992168816545
Approved
2020-03-16 07:29:46
pwdse2ce
0
WBM, PC

Progress Update : 2019-01-12
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0951041,94.3775522
1.5784329268478
Approved
2019-01-16 06:30:52
pwdse2ce
0
Shingling pc

Progress Update : 2019-01-12
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0951041,94.3775522
1.5784329268478
Approved
2019-01-16 06:31:18
pwdse2ce
0
Shingling pc

Progress Update : 2019-01-05
Construction
Phase -l
eeukld
25.10337633510905,94.36481267373654
25.095123,94.3769097
1.5250583193602
Approved
2019-01-16 06:31:40
pwdse2ce
0
Shingling pucca drain pc

Progress Update : 2019-01-05
Construction
Phase -l
eeukld
25.10337633510905,94.36481267373654
25.095123,94.3769097
1.5250583193602
Approved
2019-01-16 06:33:04
pwdse2ce
0
Shingling pucca drain pc

Progress Update : 2019-01-05
Construction
Phase -l
eeukld
25.10337633510905,94.36481267373654
25.095123,94.3769097
1.5250583193602
Approved
2019-01-16 06:33:47
pwdse2ce
0
Shingling pucca drain pc

Progress Update : 2018-10-24
Construction (Before)
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0945436,94.3714484
1.1878418770156
Approved
2020-03-16 07:28:21
pwdse2ce
0
Ew shingling wbm pc rw pucca drain approach

Progress Update : 2018-10-24
Construction 20%
Phase l
eeukld
25.10337633510905,94.36481267373654
25.0945436,94.3714484
1.1878418770156
Approved
2018-11-15 08:51:52
pwdse2ce
0
Ew shingling wbm pc rw pucca drain approach

Progress Update : 2018-10-24
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.107862,94.3761689
1.2474505403886
Approved
2019-01-16 06:36:05
pwdse2ce
0
Ew shingling wbm pc rw pucca drain approach

Progress Update : 2018-10-24
Construction
Phase l
eeukld
25.10337633510905,94.36481267373654
25.1061135,94.3679149
0.43610572160082
Approved
2019-01-16 06:36:35
pwdse2ce
0
Ew shingling WBM PC RW Pucca drain & approach road

Progress Update : 2018-10-24
Construction 20%
Phase l
eeukld
25.10337633510905,94.36481267373654
25.129652,94.3724121
3.0200959744971
Approved
2018-11-15 08:51:10
pwdse2ce
0
Ew shingling WBM PC RW Pucca drain & approach road

Progress Update : 2018-10-24
Construction 20%
Phase l
eeukld
25.10337633510905,94.36481267373654
25.1004591,94.3589216
0.67605792743459
Approved
2018-11-15 08:50:53
pwdse2ce
0
Ew shingling WBM PC RW Pucca drain & approach road

Progress Update : 2018-10-24
Construction 20%
Phase l
eeukld
25.10337633510905,94.36481267373654
25.1084129,94.3589115
0.8164806106195
Approved
2018-11-15 08:50:27
pwdse2ce
0
Ew shingling WBM PC RW Pucca drain & approach road

Foundation & Inauguration
-
-
-

-
-
-