Progress
 
 
Project Details
DAR-2018-001435
TBL/Darpan/Plan/54
Impt of Yairipok Bazar to Shikhong road-7.50km(SH:-Strengthening of road from 6.00km to 7.50km)
2018-03-21
PWD
Thoubal
161.48
121.48
State Plan
100%
Phase II
24.650051606333402,94.0959471146607
Shingling,WBM,SDC etc
Progress Update : 2019-08-29
100%
Phase II
sotbl1
24.650051606333402,94.0959471146607
24.6506778,94.0988488
0.30138792169447
Approved
2019-09-11 10:22:46
se2pwd
121.48
SDC surface of Yairipok Bazar to Shikhong road from Ch. 6.00km to 7.50 km

Progress Update : 2018-12-19
40%
Phase I
9862717924
24.650051606333402,94.0959471146607
24.64872513,94.0878713
0.82934300125501
Approved
2018-12-27 09:10:13
se2pwd
0
Shingling and WBM surface of Yairipok Bazar to Shikhong road from chainage 6.00km to 7.50km