Progress
 
 
Project Details
DAR-2018-001451
TBL/Darpan/Plan/57
Impt of Thoubal MI Road (0.00km to 10.00km)
2018-02-26
PWD
Thoubal
300.00
150
State Plan
100%
2
24.641034278861454,93.9915537930176
Shingling, WBM ,etc.
Progress Update : 2019-05-06
100%
2
9615903623
24.641034278861454,93.9915537930176
24.6442467,93.971055
2.1022384418396
Approved
2019-10-21 07:48:28
se2pwd
150
PC surface

Progress Update : 2019-03-06
55%
1
9615903623
24.641034278861454,93.9915537930176
24.6438825,93.9952539
0.49002947035356
Approved
2019-03-07 08:47:31
se2pwd
0
WBM surface

Progress Update : 2019-03-06
55%
1
9615903623
24.641034278861454,93.9915537930176
24.6388349,93.9945195
0.38683565667
Approved
2019-03-07 08:43:26
se2pwd
0
Slab culvert 1m span

Progress Update : 2019-01-23
55%
1
9615903623
24.641034278861454,93.9915537930176
24.6461488,93.9581724
3.4211965025802
Approved
2019-03-07 08:42:47
se2pwd
0
PC surface

Foundation & Inauguration
-
-
-

-
-
-