Progress
 
 
Project Details
DAR-2019-000024
SPT/DC Bunglow/11
Senapati Hd. Qtr. Roads (NH-2 to DC & SP Bunglow via DC Complex and Colony road)
2016-03-29
PWD
Senapati
276.10
214.54
State Plan
Photo before start of work: Completed Now
Final
25.269977914927615,94.02043032646202
Road Pavement.
Progress Update : 2019-01-24
Photo before start of work: Completed Now
Final
eesptd
25.269977914927615,94.02043032646202
25.2726201,94.0246887
0.51926903100732
Approved
2019-02-22 10:27:36
pwdse2ce
0
WBM and premix carpeting

Progress Update : 2019-01-24
Completed
Final
eesptd
25.269977914927615,94.02043032646202
25.2693317,94.018066
0.24835343310523
Approved
2019-02-22 10:28:27
pwdse2ce
0
WBM and premix carpeting

Progress Update : 2019-01-24
Photo before start of work: Completed
Final
eesptd
25.269977914927615,94.02043032646202
25.2714722,94.0199114
0.17414922852832
Approved
2019-02-22 10:28:10
pwdse2ce
0
WBM and premix carpeting

Progress Update : 2019-01-24
Completed
Final
eesptd
25.269977914927615,94.02043032646202
25.2723976,94.0192638
0.2934996595651
Approved
2019-01-28 08:07:57
pwdse2ce
0
WBM and premix carpeting

Foundation & Inauguration
-
-
-

-
-
-