DAR-2019-000478
JNIMS/Laundry Building
Const of 2nd floor above existing Laundry block,effluent treatment tank,outlet drain,flooring of ground floor and G.I pipe line connection at JNIMS.
2018-09-06
PWD
Imphal-East
56.49
19.56
State Plan
Completed
II
24.810103615809492,93.96125261719658
Constn. of RCC columns,beams,tile flooring, tubular truss, DYNA roof,effluent treatment tank,outlet drain,flooring of ground floor and G.I pipe line connection ,etc.
Progress Update : 2020-12-14
Completed
II
7085969655
24.810103615809492,93.96125261719658
24.8104309,93.96337908
0.21768090542816
Approved
2020-12-21 06:55:54
se2pwd
19.56
Dyna sheet roofing over steel tubular trusses, tile flooring etc

Progress Update : 2020-12-14
Completed
II
7085969655
24.810103615809492,93.96125261719658
24.81040352,93.96327066
0.20638680953699
Approved
2020-12-21 06:55:18
se2pwd
19.56
Dyna sheet roofing over steel tubular trusses, tile flooring etc

Progress Update : 2020-12-14
Completed
II
7085969655
24.810103615809492,93.96125261719658
24.81042248,93.9629024
0.17024047306863
Approved
2020-12-21 06:54:29
se2pwd
19.56
Dyna sheet roofing over steel tubular trusses, tile flooring etc

Progress Update : 2019-09-24
Ongoing
1
7085969655
24.810103615809492,93.96125261719658
24.809561,93.9596277
0.17474455290044
Approved
2019-09-26 08:56:31
se2pwd
0
Rcc columns, beams, flooring of ground floor etc

Progress Update : 2019-09-24
Ongoing
1
7085969655
24.810103615809492,93.96125261719658
24.809561,93.9596277
0.17474455290044
Approved
2019-09-26 08:57:55
se2pwd
0
Rcc columns, beams, flooring of ground floor etc

Progress Update : 2019-09-24
Ongoing
1
7085969655
24.810103615809492,93.96125261719658
24.8105627,93.9637713
0.25927749736128
Approved
2019-09-26 08:59:16
se2pwd
0
Rcc columns, beams, flooring of ground floor etc

Foundation & Inauguration
-
-
-

-
-
-