Progress
 
 
Project Details
DAR-2019-000493
IWD/Khurkhul-Sairok Bridge/128
Improvement of Khurkhul to Sairok bridge(SB) road
2018-02-26
PWD
Imphal-West
225.00
82
State Plan
50% completed
---
24.91590589193279,93.84791221804653
Progress Update : 2025-01-15
50% completed
---
geetkh
24.91590589193279,93.84791221804653
24.911268,93.8573094
1.0788642945679
Approved
82
Roadwork

Progress Update : 2025-01-15
50% Completed
Nil
geetkh
24.91590589193279,93.84791221804653
24.909407,93.8614926
1.5484429140213
Approved
2026-06-08 09:08:49
se1pwd
82
Road work

Progress Update : 2019-10-12
In Progress
NA
siddhartha
24.91590589193279,93.84791221804653
24.9148109,93.8383257
0.97435357811269
Approved
40
RCC Culvert

Progress Update : 2019-10-12
In Progress
NA
siddhartha
24.91590589193279,93.84791221804653
24.9155905,93.8484969
0.068600705709112
Approved
2020-02-19 10:03:00
se1pwd
0
RCC Culvert

Progress Update : 2019-10-12
In Progress
NA
siddhartha
24.91590589193279,93.84791221804653
24.9381664,93.841198
2.5660549613291
Approved
2020-02-19 10:02:08
se1pwd
0
RCC Culvert

Foundation & Inauguration
-
-
-

-
-
-