DAR-2020-000217
EE/BPR/Kabowakching high school/
Maint. of IVR from Kabowakching High School to Kabowakching Awang Leikai & Kabowakching Maning Leikai(SH: GSB).
2019-03-08
PWD
Bishnupur
20.00
6.50
State Plan
Completed
1st
24.72125970978032,93.80817705242309
Scope :- Surface dressing on shoulder both side 1m wide, 2413.70 length & GSB3m wide, 0.15m thick 2413.70m length
Progress Update : 2020-02-27
Completed
1st
lalit
24.72125970978032,93.80817705242309
24.719855189323,93.804364800453
0.41550232967567
Approved
2021-12-09 08:53:16
se3pwd
0
Surface dressing and gsb

Progress Update : 2020-02-27
Completed
1st
lalit
24.72125970978032,93.80817705242309
24.722553491592,93.807524442673
0.15823642946144
Approved
2021-12-09 08:53:34
se3pwd
0
Surface dressing and gsb

Progress Update : 2020-02-27
Completed
1st
lalit
24.72125970978032,93.80817705242309
24.720767140388,93.808650970459
0.07273719940638
Approved
2020-02-28 06:21:13
se3pwd
0
Surface dressing and gsb

Progress Update : 2020-02-27
Completed
1st
lalit
24.72125970978032,93.80817705242309
24.720209240913,93.809375166893
0.16818376829557
Approved
2020-02-28 06:22:15
se3pwd
0
Surface dressing and gsb