Progress
 
 
Project Details
DAR-2020-000298
SPT/Emishiiphro to Taphou Ngathang/43
Impvt. of road from Emesiiphro to Taphou Ngathang
2019-03-16
PWD
Senapati
60.00
15.37
State Plan
Complete
Final
25.25538,94.0099
Earth Work, Shingling, WBM & Culvert
Progress Update : 2023-03-04
Complete
Final
eesptd
25.25538,94.0099
25.2596629,93.997889
1.2983129917552
Approved
2023-03-13 06:57:26
pwdse2ce
15.37
PC & SC - completed

Progress Update : 2023-03-04
Complete
Final
eesptd
25.25538,94.0099
25.2456953,94.0084158
1.0871328260463
Approved
2023-03-13 07:00:42
pwdse2ce
15.37
Completed - PC & SC

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2553589,94.009879
0.0031570712731699
Approved
2020-03-13 07:46:14
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2553589,94.009879
0.0031570712731699
Approved
2020-03-13 07:45:34
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2539233,94.0134126
0.38859861798417
Approved
2020-03-13 07:44:36
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2536233,94.0040712
0.61784536878005
Approved
2020-03-13 07:43:46
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2518878,93.9982633
1.2329605020238
Approved
2020-03-13 07:43:07
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Progress Update : 2020-03-13
In progress
First
eesptd
25.25538,94.0099
25.2518878,93.9982633
1.2329605020238
Approved
2020-03-13 07:41:34
pwdse2ce
0
E/W, shingling,wBM,premix carpet,pipe culvert

Foundation & Inauguration
-
-
-

-
-
-