Progress
 
 
Project Details
DAR-2020-000364
PZL/JT-Muolkhangthol/3
Constn. of road from J-T road to Muolkhangthol village (4 Km) with construction of 2 culverts
2019-03-01
PWD
Pherzawl
80.00
68
State Plan
Completed
Phase 2
24.656247691179786,93.11833761688841
Progress Update : 2021-02-12
Completed
Phase 2
ahamad
24.656247691179786,93.11833761688841
24.6537443,93.1163452
0.34353609583388
Approved
2022-10-17 10:09:21
pwdse2ce
0
CD works completed

Progress Update : 2021-02-12
The work has been fully completed
Phase 2
ahamad
24.656247691179786,93.11833761688841
24.65779933,93.11302622
0.56377154214682
Approved
2024-07-30 09:41:19
pwdse2ce
68
Sanction awaited for second payment

Progress Update : 2021-02-12
Completed
Phase 2
ahamad
24.656247691179786,93.11833761688841
24.6528387,93.1063177
1.2724227564805
Approved
2022-10-17 10:10:04
pwdse2ce
0
E/W and CD Works completed

Progress Update : 2021-02-12
Completed
Phase 2
ahamad
24.656247691179786,93.11833761688841
24.6528387,93.1063177
1.2724227564805
Approved
2022-10-17 10:08:48
pwdse2ce
0
Culverts completed

Progress Update : 2020-05-28
100% completed
First phase
soccpr1
24.656247691179786,93.11833761688841
24.6680576,93.1053777
1.8545331441848
Approved
2024-07-30 09:42:20
pwdse2ce
68

Progress Update : 2020-05-28
100% completed
First phase
soccpr1
24.656247691179786,93.11833761688841
24.65810513,93.11620081
0.29879474209779
Approved
2024-07-30 09:43:04
pwdse2ce
68
Completed

Foundation & Inauguration
-
-
-

-
-
-