Progress
 
 
Project Details
DAR-2021-000410
JJM/KANGPOKPI/NEW KEITHELMANBI/46
Water Supply Scheme at New Keithelmanbi
2020-07-15
PHED
Kangpokpi
45.00
0.00
CSS / CPS
Rinforcement
Phase 2
24.684890060331245,93.73272333442382
Construction of Intake, Service Reservoir, Settling Tank and Distribution Tank
Progress Update : 2021-04-12
Rinforcement
Phase 2
deepakl
24.684890060331245,93.73272333442382
24.7745058,93.7891527
11.478935502197
Approved
2022-05-24 06:08:53
eekpiphed
0
Settling tank

Foundation & Inauguration
-
-
-

-
-
-