Progress
 
 
Project Details
DAR-2023-000477
EE/BPR/Constn Chaobi Mapa Shetapur Dam
Construction of protection work at Chaobi Mapa along Shetapur Dam road
23/02/2023
PWD
Bishnupur
76.00
44
State Plan
100pc completed
phasell
24.433636694905367,93.80029606819167
CC works
Progress Update : 19/01/2026
100pc completed
phasell
lalit
24.433636694905367,93.80029606819167
24.4338517,93.8003997
0.026106813892631
44
construction of retaining wall

Progress Update : 26/03/2023
In progress
Phase I
lalit
24.433636694905367,93.80029606819167
24.4262474,93.8078197
1.1203391340319
44
Road work