Progress
 
 
Project Details
DAR-2023-000505
EE/BPR/Impvt Chingmei Bazar to Chingmei Makha
Improvement of road from Chingmei Bazar to Chingmei Makha
2023-02-23
PWD
Bishnupur
75.00
52.88
State Plan
completed
2
24.475485506261105,93.8104562759396
GSB WBM PC
Progress Update : 2025-02-20
completed
2
lalit
24.475485506261105,93.8104562759396
24.4766333,93.8081567
0.2654092780069
Approved
2025-03-06 11:29:45
se3pwd
52.88
road work

Progress Update : 2024-09-26
60pc
2
lalit
24.475485506261105,93.8104562759396
24.4766565,93.8077095
0.306949749942
Approved
2024-09-26 08:05:21
se3pwd
16.93
road work

Foundation & Inauguration
-
-
-

-
-
-