Progress
 
 
Project Details
DAR-2024-000148
SE-I/IW/DRP/2023-24/R1/135-25 Tera Sapam
Improvement of Tera Sapam Leirak internal Roads
2023-11-09
PWD
Imphal-West
150.00
120
State Plan
completed
nil
24.79392,93.91778
Impvt of Road
Progress Update : 2026-01-29
completed
nil
pradeepkh
24.79392,93.91778
24.7923302,93.9155852
0.28342486545695
Approved
2026-01-29 10:05:20
se1pwd
120
road work

Progress Update : 2024-03-19
In progress
Nil
pradeepkh
24.79392,93.91778
24.7924872,93.9182676
0.1667420922798
Approved
2024-03-20 07:34:22
se1pwd
0
WBM surface

Foundation & Inauguration
-
-
-

-
-
-