DAR-2024-000187
EE/BPR/Impvt Ningthoukhong Kha IVRs
Improvement of Ningthoukhong Kha IVRs (Portion-1)-3km
2023-11-09
PWD
Bishnupur
110.00
88.37
State Plan
completed
phase 1
24.568536275501096,93.76748614992066
road work
Progress Update : 2026-02-05
completed
phase 1
lalit
24.568536275501096,93.76748614992066
24.5709632,93.7715193
0.48903165738037
Approved
2026-02-05 16:56:34
se3pwd
88.37
gsb wbm p.c np3 etc.

Progress Update : 2024-08-09
100pc
phase 1
lalit
24.568536275501096,93.76748614992066
24.5696213,93.7676016
0.12120699021115
Approved
2025-02-18 13:43:35
se3pwd
22
scarifying gsb wbm PC etc.

Foundation & Inauguration
-
-
-

-
-
-