DAR-2024-000388
SE-I/BDG/DRP/2022-23/C1/389-1 Moirangthong
Construction of Moirangthong Bride over Nambul River at Takyel Khongbal
23/02/2023
PWD
Imphal-West
180.00
153.5
State Plan
Completed
Final Phase
24.80722,93.89783
Construction of Bridge
Progress Update : 30/12/2025
Completed
Final Phase
so1brd
24.80722,93.89783
24.8071349,93.8977309
0.013768556279179
153.5
Pile Foundation completed, pile cap completed

Progress Update : 03/03/2025
ongoing
2
so1brd
24.80722,93.89783
24.8072495,93.8976387
0.019584281036173
25
Abutment Pile, Peir Pile Work completed, Abutment pile cap reinforcement work completed

Progress Update : 20/03/2024
Ongoing
First
so1brd3
24.80722,93.89783
24.8073586,93.8977029
0.02005129398474
0
Pile Foundation