Progress
 
 
Project Details
DAR-2024-000395
EE/BPR/Major Renovatn AE(PWD) office Staff
Major Renovation of AE(PWD)office & Staff Quarter at Moirang
29/12/2023
PWD
Bishnupur
90.00
81.39
State Plan
completed
phase lll
24.49659563117839,93.76706874470518
Renovation
Progress Update : 02/12/2025
completed
phase lll
lalit
24.49659563117839,93.76706874470518
24.4969574,93.7676419
0.070577279358091
81.39
construction of Ae office and staff quarter

Progress Update : 02/12/2025
completed
phase lll
lalit
24.49659563117839,93.76706874470518
24.4968842,93.7676353
0.065693300174966
81.39
construction of Ae office and staff quarter

Progress Update : 28/10/2024
work is in progress
2
lalit
24.49659563117839,93.76706874470518
24.4968997,93.7673439
0.043796722331906
0
building work

Progress Update : 20/03/2024
Work is in progress60pc
1
lalit
24.49659563117839,93.76706874470518
24.4967097,93.7673473
0.030906769263206
0
Construction of Ae office