41 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | X | |
42 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | X | |
43 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | X | |
44 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | X | |
45 | MSPCLC30 | Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV LILO line & related civil works at Paoyi, Ukhrul District. | POWER (MSPCL) | Ukhrul | Y | X | 02/03/2019 |
46 | MSPCLC19 | Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Gumnom | POWER (MSPCL) | Ukhrul | Y | X | |
47 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | X | |
48 | SS/D-IV/DIET IMPHAL WEST TEdn | Implementation of Samagra Shiksha (Teacher Education) for the Year 2022-23 at DIET Imphal West, Manipur. | Education (S) | Imphal-West | y | j | |
49 | SMDC/KIYAMGEI MADRASSA/HS | Construction of 1 one Library and Drinking water, Imphal East | Edu (S) - SSA & RMSA | Imphal-East | y | h | |
50 | STG-LILONG Hr Sec-2019-20 | Lilong Hr. Sec. School 2019-20 1ACR 1physic lab 2Boys Toilet | Edu (S) - SSA & RMSA | Imphal-West | y | b | |
51 | MSPCLC28 | Re-stringing & strengthening 33 KV line from Bishnupur to Churachandpur via Ningthoukhong & Moirang | POWER (MSPCL) | Bishnupur | Y | 50% | 05/03/2019 |
52 | MSPCLC28 | Re-stringing & strengthening 33 KV line from Bishnupur to Churachandpur via Ningthoukhong & Moirang | POWER (MSPCL) | Bishnupur | Y | 50% | |
53 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | 50% | 04/03/2019 |
54 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | 50% | |
55 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | 50% | |
56 | MSPCLC15 | Construction of 33 kV DC line on steel tubular pole from 132/33 kV Sub-Station Thoubal to 33/11 kV Sub-Station Thoubal (Old) on turn key basis | POWER (MSPCL) | Thoubal | Y | 100 % | 06/03/2020 |
57 | MSPCLC28 | Re-stringing & strengthening 33 KV line from Bishnupur to Churachandpur via Ningthoukhong & Moirang | POWER (MSPCL) | Bishnupur | Y | 50% | 05/03/2019 |
58 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | X | |
59 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | X | |
60 | MSPCLC31 | Re-stringing & strengthening 33 KV line from Churachandpur to Singhat. | POWER (MSPCL) | Churachandpur | Y | X | |