#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
3561EE/HS/Impvt Southern portion Chajing mamang Improvement of Southern portion of Chajing Mamang Leikai roadPWDImphal-West1In progress10/10/2024
3562EE/HS/Impvt Wahengbam Sahadeba LeirakImpvt. of Wahengbam Sahadeba Leirak,Wahengbam Khongnem Leirak,Wahengbam Manitombi Leirak,Wahengbam Amu Leirak of Wangoi Wahengbam Leikai PWDImphal-Westphase 1completed 10/10/2024
3563EE/HS/Impvt Chabungbam Nodiachanda LeirakImpvt. of Chabungbam Nodiachanda Leirak,Yumnam Menjor Leirak at Yumnam HuidromPWDImphal-Westphase 1completed 10/10/2024
3564EE/HS/Impvt Moirangmayum Ram Singh LeiralkImpvt. of Moirangmayum Ram Singh Leirak,Mary Leirak &Sapam Sobha Leirak of Samurou Awang LeikaiPWDImphal-Westphase 1completed 10/10/2024
3565MSPDCL-STATEPLAN-107Supply of 35 nos of 250 KVA DTR, 60 nos of 100 KVA DTR, 30 nos of 63 KVA DTR & 25 nos of 25 KVA DTR as per latest amendmentPOWER (MSPDCL)Imphal-WestPhase 1Ongoing10/10/2024
3566RR/22-DI/MultiGPWomenCollege/IWRenovation/Repairing/Construction of Toilet/Furnishing of Multi-Purpose Hall of GP Womens College, Imphal West, ManipurEducation (S)Imphal-Westcompleted nil09/10/2024
3567RR/22-DI/MultiGPWomenCollege/IWRenovation/Repairing/Construction of Toilet/Furnishing of Multi-Purpose Hall of GP Womens College, Imphal West, ManipurEducation (S)Imphal-Westnilcompleted 09/10/2024
3568RR/22-DI/MultiGPWomenCollege/IWRenovation/Repairing/Construction of Toilet/Furnishing of Multi-Purpose Hall of GP Womens College, Imphal West, ManipurEducation (S)Imphal-Westnilcompleted 09/10/2024
3569UKL/DAR/2022-23/R2/9A CRIF TolloiJn SomdalImpvt of road from Ngaimu/Tolloi Junction to Somdal 18.00 Km under CRIFPWDUkhrulPhase 156.12%09/10/2024
3570UKL/DAR/2022-23/R2/9A CRIF TolloiJn SomdalImpvt of road from Ngaimu/Tolloi Junction to Somdal 18.00 Km under CRIFPWDUkhrulPhase 156.12%09/10/2024
3571UKL/DAR/2022-23/R2/9A CRIF TolloiJn SomdalImpvt of road from Ngaimu/Tolloi Junction to Somdal 18.00 Km under CRIFPWDUkhrulPhase 156.12%09/10/2024
3572UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3573UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3574UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3575UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3576UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3577UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3578UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09%09/10/2024
3579UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 1100% completed09/10/2024
3580UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024