7401UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul2completed17/07/2024
7402UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul1completed 17/07/2024
7403UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul2completed 17/07/2024
7404UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul2completed 17/07/2024
7405UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul2completed 17/07/2024
7406IWD/Babupara Internal road-DC Office/268Impvt. of Babubara Internal Road leading to DC OfficePWDImphal-West---Completed17/07/2024
7407IWD/Nepra Manjor Internal/269Impvt. of Nepra Manjor internal RoadPWDImphal-West---Completed17/07/2024
7408SE-I/IW/DRP/2023-24/R1/128-18 Mayanglangjing Improvement of IVR at Mayanglangjing Taning from Mayanglangjing Bridge to Awang Leikai to Makha Leikai internal road (SH:- WBM & Premix Carpeting)PWDImphal-West--Completed17/07/2024
7409IWD/Amudon Internal road/266Improvement of Amudon Internal roadsPWDImphal-West---Completed17/07/2024
7410IED/Approach road-Shishu Nistha Niketan/896Constn. of approach road from Tinsid road leading to Shishu Nistha Niketan, Chinghei Ching, Imphal East.PWDImphal-East---Completed17/07/2024
7411IED/ Kongba Maril Khabeisoi(western)/901Impvt. of Kongba Maril Khabeisoi road (Western side of Kongba riverPWDImphal-East--Completed 17/07/2024
7412IED/Bamon_Tharoijam via Paonam leirak/895Impvt. of Bamon leirak, Tharoijam leirak via Paonam leirakPWDImphal-East--completed17/07/2024
7413IED/Return Wall-Top Khongnangkhong Bridge/862Contn. of Return Wall at Top Khongnangkhong Bridge, Kshetrigao A/C, Imphal eastPWDImphal-East--Completed 17/07/2024
7414IED/Porompat road No. II/902Impvt. of Porompat road No. IIPWDImphal-East--Completed 16/07/2024
7415IED/Standard College Road/882Improvement of Standard College Road.PWDImphal-East--Completed 16/07/2024
7416IED/Kongpal Iranpham-Thambalkhong/891Improvement of Road from Kongpal Iranpham Thong to Thambalkhong eastern side Kongba BazarPWDImphal-East--Completed16/07/2024
7417UKL/SE-IV/Luimeirui to Khayang rover tuso/39Impvt. of road from Luimeirui to Khayang Rover PMGSY road North TusomPWDUkhrulPhase 280%16/07/2024
7418UKL/SE-IV/Luimeirui to Khayang rover tuso/39Impvt. of road from Luimeirui to Khayang Rover PMGSY road North TusomPWDUkhrulPhase 280%16/07/2024
7419UKL/SE-IV/Luimeirui to Khayang rover tuso/39Impvt. of road from Luimeirui to Khayang Rover PMGSY road North TusomPWDUkhrulPhase 280%16/07/2024
7420UKL/Tolloi NH 102A junction to Phungcham/61Construction of road from Tolloi NH 102A Junction to PhungchamPWDUkhrulPhase 280%16/07/2024