1021 | MSPCLC48 | Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Kachai, Ukhrul District on turn key basis | POWER (MSPCL) | Ukhrul | x | 70% | 01/03/2025 |
1022 | MSPCLC45 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Akampat, Imphal East District on turn key | POWER (MSPCL) | Imphal-East | x | 95% | 01/03/2025 |
1023 | MSPCLC53 | Installation of 2x2.5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Nampisha, Kamjong District on turn key basis | POWER (MSPCL) | Kamjong | x | 60% | 01/03/2025 |
1024 | MSPCLC43 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Sanakeithel, Ukhrul District . | POWER (MSPCL) | Ukhrul | x | 70 | 01/03/2025 |
1025 | MSPCLC44 | Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Somdal, Ukhrul District on turn key basis | POWER (MSPCL) | Ukhrul | 30 | 70 | 01/03/2025 |
1026 | MSPCLC39 | Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basis | POWER (MSPCL) | Ukhrul | 1 | 80 | 01/03/2025 |
1027 | MSPCLC40 | Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Joujangtek, Noney District on turn key basis | POWER (MSPCL) | Noney | x | 60 | 01/03/2025 |
1028 | MSPCLC47 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Oinam, Senapati District on turn key basis | POWER (MSPCL) | Senapati | x | 85 | 01/03/2025 |
1029 | MSPCLC29 | Installation of 2x2.25 MVA, 33 kV LILO line & related civil works at Thuyeng, Senapati District. | POWER (MSPCL) | Senapati | x | 85 | 01/03/2025 |
1030 | IED/Kongba-Naharup Pangong/413 | Impvt. of Kongba naharup Pangong road | PWD | Imphal-East | --- | Completed | 28/02/2025 |
1031 | IED/Naharup Thong-Makha Pat/407 | Impvt. of road from Naharup Thong to Makha Pat Eastern side - 1.5 km | PWD | Imphal-East | --- | Completed | 28/02/2025 |
1032 | IED/Thawanthaba road/409 | Impvt. of road at Thawanthaba road - 1.00 kms | PWD | Imphal-East | --- | Completed | 28/02/2025 |
1033 | BRD/LEISHANG-HIDEN/2 | Construction of Leishang Hiden Bridge at Pal Ahanbi | PWD | Imphal-East | .--- | completed | 28/02/2025 |
1034 | BRD/LEISHANG-HIDEN/2 | Construction of Leishang Hiden Bridge at Pal Ahanbi | PWD | Imphal-East | --- | Completed | 28/02/2025 |
1035 | SE-I/DRP/2023-24/R1-69 -drain at AT Line | Improvement of road and drain at AT Line | PWD | Imphal-East | --- | 100% | 28/02/2025 |
1036 | SE-I/DRP/2023-24/Rc-78 -Lei Ingkhol 1m SC | Construction of drain at Chingmeirong Lei Ingkhol including 1 m span RCC slab culvert | PWD | Imphal-East | --- | 100% | 28/02/2025 |
1037 | RMSA/D-2/Lamding 1ACR LAB- TBL | Infrastructure Development of School under RMSA 2021-22 at Lamding Hr. Sec. School, Thoubal, Manipur. | Education (S) | Thoubal | nil | Completed | 28/02/2025 |
1038 | RMSA/D-2/Lamding 1ACR LAB- TBL | Infrastructure Development of School under RMSA 2021-22 at Lamding Hr. Sec. School, Thoubal, Manipur. | Education (S) | Thoubal | nil | Completed | 28/02/2025 |
1039 | RMSA/D-2/Lamding 1ACR LAB- TBL | Infrastructure Development of School under RMSA 2021-22 at Lamding Hr. Sec. School, Thoubal, Manipur. | Education (S) | Thoubal | nil | Completed | 28/02/2025 |
1040 | RMSA/D-2/Lamding 1ACR LAB- TBL | Infrastructure Development of School under RMSA 2021-22 at Lamding Hr. Sec. School, Thoubal, Manipur. | Education (S) | Thoubal | nil | Completed | 28/02/2025 |